Project Manager: Thomas J. Tibbs
Total Project Value: $909 K
In 2023, Mark Cerrone, Inc. undertook the installation of REDI Containment walls at Olcott Harbor in New York. This project was part of a broader initiative to enhance the harbor’s infrastructure and protect it from flooding and erosion. The work involved constructing sheet pile walls, stop logs, retaining walls, concrete slabs, fencing, and rip rap along the east and west shorelines. These improvements aimed to bolster the harbor’s resilience against extreme weather events and ensure the safety and functionality of the area for both residents and visitors. The project was executed efficiently, showcasing Mark Cerrone, Inc.’s expertise in handling complex construction tasks and contributing to the long-term sustainability of Olcott Harbor.