Project Manager: Chris Ganje

Total Project Value: $1.3 M

In 2023, Mark Cerrone, Inc. undertook the rehabilitation of the bus loop at the University at Buffalo. This project involved the removal of existing concrete bus loop pavement, sidewalks, curbs, and drainage structures. The work included installing new concrete pavement, sidewalks, and curbs, as well as upgrading the storm sewer system with new pipes and drainage structures. The project aimed to improve the functionality and safety of the bus loop, providing a better experience for students and visitors. Mark Cerrone, Inc.’s expertise ensured the project was completed efficiently and to high standards, contributing to the overall enhancement of the university’s transportation infrastructure.